Tuesday, February 28, 2017

The College of Pharmacy Building project is moving forward! The project is currently in the deep foundations stage, which will be completed in March. During this phase, a total of 80 shafts were drilled into bedrock to secure the foundation.

Following the deep foundations stage, the project will be turned over to Miron Construction, the contractor that has been awarded the remainder of the project construction.